Timeline
Subject to
planning*

Autumn
2024
Places for Barnet is established to deliver much needed housing and community assets for the borough. Work on the vision for Cherry Tree Quarter commenced.

Winter 2024
Initial surveys of the site are undertaken and some feasibility work is completed.

Winter
2024 – start 2025
Commencement of concept design
proposals to help inform consultation.

Feb 2025
Public consultation on the plans for the future of the site with the area's residents, businesses and stakeholders.

March 2025
Following further consultation with local stakeholders, start to prepare more detailed planning drawings and obtain wider input from a team of specialist consultants.

9th April
2025
Ingram Road residents meeting.

23rd & 26th
April 2025
We’re here: A further round of public engagement events.

May
2025
Finalisation of design proposals.

Early
Summer
Submission of a planning application.

Summer
2025

Winter
2025/ 2026
Site mobilisation/ early construction work begins.*

2028
First residents move in.*